The U.S. Senate voted 62 to 33 on Nov. 19 to speed federal approval of energy projects and charge large data centers a greater share of the cost of expanding the electric grid. Oregon Sens. Ron Wyden and Jeff Merkley opposed the measure after the Senate declined to vote on a construction ban that would have put federal land near Hermiston off limits to data center developers.
The Bipartisan American Affordability and Jobs Act goes to the House with support from both parties for shorter federal reviews of power plants, pipelines and transmission lines. Wyden and Merkley backed provisions to protect electricity customers from the cost of serving large data centers. Both pressed for changes governing the use of public land, the role of tribal governments in federal project reviews and the administration’s authority over clean energy projects.
“Permitting reform can and must be done without giving public lands away to tech giants, stomping all over tribal sovereignty, and relying on Trump to uphold his end of the deal after he spent the last two years attacking clean energy projects,” Wyden said. “I urge the House to resolve these substantial flaws before passing it into law.”
The parcel near Hermiston came to light in September as a potential site for one of as many as 12 data centers the Trump administration was considering across six Western states. More than 17,000 acres were under consideration across the region. Wyden began pressing for a construction ban that month. The Oregon parcel’s future remains open after the Senate vote.
Wyden’s amendment would have prohibited data center construction in national forests and on land managed by the Interior Department. The restriction would also have followed the property after a sale or transfer. If a developer later used the land for a data center, ownership would revert to the United States unless Congress had specifically authorized that use. Wyden excluded Indian reservations and certain lands held in trust for tribes or individual tribal members.
Oregon utility regulators have already settled who will pay when Pacific Power expands its system to serve a new data center. Beginning Jan. 1, 2027, qualifying facilities in the utility’s Oregon territory must sign long-term agreements covering the infrastructure and electricity service their operations require. The Oregon Public Utility Commission approved the rates under the state’s 2025 POWER Act.
The rates cover new computing and data-processing facilities capable of drawing at least 20 megawatts. Pacific Power will bill those customers directly for the cost of serving them. Very large data centers will also pay one cent per kilowatt-hour toward energy efficiency improvements, essential home repairs and other work to reduce electricity costs for Oregon households with the greatest financial need.
In the Senate, the permitting package drew backing from both the American Clean Power Association and the American Petroleum Institute. Wind and solar developers depend on transmission lines to carry electricity from generating sites to customers. Pipeline and power plant developers also have a financial stake in how long federal reviews take and whether an agency can later revoke a permit. Supporters argued that firmer construction schedules would make financing easier to secure and bring new energy supplies into service sooner.
Northwest tribal leaders raised concerns about what shorter reviews would mean on the ground, particularly where a proposed construction route crosses an ancestral site or threatens a water supply. Merkley said tribal governments had too little opportunity to shape the legislation. He also sought to exclude data centers from new protections against permit revocation and to limit the administration’s authority to cancel clean energy grants on political grounds.
The House can send the Senate measure to the president as written. Adding Wyden’s public lands ban or changing the terms of federal project reviews would send it back to the Senate. For now, the parcel near Hermiston remains a prospective site. Pacific Power’s January rates, approved under Oregon law, take effect independently of the vote in Congress.