Google has entered into a landmark electricity agreement with Quaise Energy to develop geothermal power near Newberry Volcano in Central Oregon, committing to purchase 50 megawatts of electricity from an emerging technology capable of generating power from underground rock formations reaching temperatures of nearly 1,000 degrees Fahrenheit.
The agreement, announced Tuesday, November 17, 2026, establishes a commercial commitment to Project Obsidian, a proposed geothermal generating facility on the southern flank of Newberry Volcano near La Pine in Deschutes County. The development is scheduled to begin delivering electricity as early as 2030, with plans for substantial expansion that could eventually establish one of the largest geothermal generating operations in the United States.
The initial electricity purchase will support Google’s three data center campuses in The Dalles, where the company has maintained a significant computing and technology presence since 2006. The agreement represents the first announced commercial-scale power purchase involving superhot rock geothermal technology, an advanced method of electricity generation now moving toward commercial development.
Quaise has outlined a three-phase expansion program beginning with 50 megawatts, followed by 250 megawatts and an eventual generating target exceeding 1,000 megawatts. At maximum continuous output, the initial facility could produce approximately 438 million kilowatt-hours annually. The proposed one-gigawatt expansion could generate as much as 8.76 billion kilowatt-hours per year, equivalent to the annual electricity consumption of approximately one million average American households.
Newberry Volcano, located south of Bend, has emerged as a major location for geothermal exploration because of extensive underground heat resources associated with its volcanic history. The volcano last erupted approximately 1,300 years ago and remains geologically active, with exceptionally high temperatures recorded beneath the surrounding landscape.
Project Obsidian will target underground rock formations reaching temperatures between approximately 572 and 932 degrees Fahrenheit. The development will extract thermal energy from those formations to generate electricity continuously, without relying on fossil-fuel combustion or weather-dependent generating conditions.
The project will initially use conventional drilling equipment, with Quaise planning to introduce experimental millimeter-wave drilling technology during a subsequent development phase. The advanced system, originating from research associated with the Massachusetts Institute of Technology, uses concentrated electromagnetic energy to penetrate underground rock formations at extreme temperatures and depths.
Quaise is pursuing the technology to increase geothermal generating capacity and expand access to underground energy resources beyond locations currently served by conventional geothermal facilities. The company estimates that superhot geothermal wells could eventually produce as much as 10 times the electricity generated by traditional geothermal wells, although commercial production at those levels has not yet been demonstrated at Project Obsidian.
The proposed development has attracted substantial private investment, including a $180 million Series B financing round completed by Quaise in August 2026. The financing included a $35 million investment from Nabors Industries, an international drilling and energy technology company.
Construction of the initial geothermal facility has been associated with an estimated cost of approximately $350 million. The long-term electricity agreement with Google has been reported to carry a potential value exceeding $500 million, although neither company has publicly disclosed the contract’s financial terms.
Google’s participation extends its investment in Oregon’s technology and energy infrastructure. The company established its first company-owned data center in The Dalles in 2006 and has since expanded to three campuses, reporting more than $7 billion invested in Oregon over the past two decades.
The company’s Oregon data center operations have reached an 83 percent carbon-free electricity level under its energy accounting. The Project Obsidian agreement will add a prospective source of continuous geothermal electricity to support those facilities as demand increases for cloud computing, artificial intelligence and other large-scale data processing operations.
The Central Oregon development is also expected to bring additional employment and infrastructure construction to Deschutes County. Quaise projects approximately 200 to 400 construction jobs during the initial development and more than 50 permanent skilled positions involving engineering, geothermal operations, equipment maintenance and technical services.
Approximately 10 miles of new electrical transmission infrastructure are planned to connect the generating facility with an existing substation near La Pine. Electricity produced at Project Obsidian would enter the regional power network for delivery through the interconnected electrical system serving Oregon and the Pacific Northwest.
The planned expansion arrives as Oregon utilities face increasing electricity demand and growing requirements for additional generating capacity and transmission infrastructure. Data center development, industrial operations and population growth have contributed to rising demand across the region.
Project Obsidian would add continuous geothermal generation to Oregon’s electricity portfolio, which has historically relied heavily on hydroelectric facilities alongside natural gas, wind, solar and other generating resources. Geothermal electricity accounted for approximately 0.1 percent of Oregon’s electricity use in 2024.
The proposed facility’s effect on residential electricity rates remains undetermined. Construction costs, utility arrangements, transmission expenses and future operating performance will influence the financial results of the development. No specific reduction in household electricity rates has been established under the agreement.
Environmental and regulatory requirements will also remain central to the project’s development. Geothermal drilling and underground fluid circulation require evaluation of water resources, groundwater protection, geological conditions and potential induced seismic activity. Construction will also involve land development and electrical transmission infrastructure.
Newberry Volcano has attracted additional geothermal investment beyond Project Obsidian. Mazama Energy is pursuing superhot geothermal development in the same volcanic region, contributing to a growing concentration of advanced geothermal projects in Central Oregon.
Elsewhere in the United States, Fervo Energy and other developers are advancing enhanced geothermal operations intended to increase commercial electricity generation from underground heat resources.
Quaise has identified the broader Newberry geothermal basin as a potential resource capable of eventually supporting as much as 10 gigawatts of generating capacity. The estimate remains a long-term development projection, with future expansion dependent on additional exploration, commercial performance, financing and infrastructure investment.
The company is also developing its advanced drilling technology for potential application outside volcanic regions, with the objective of accessing geothermal resources at greater depths across a wider geographical area.
Project Obsidian’s initial 50-megawatt development remains in the planning and development stages, with commercial electricity deliveries anticipated as early as 2030. Drilling performance, construction financing, environmental approvals and transmission development will determine the schedule for bringing the facility into operation.
The November 17 agreement establishes Google as a prospective commercial purchaser of electricity from one of Oregon’s most ambitious geothermal developments, bringing a major technology company into a Central Oregon energy project with plans for substantial generating capacity, private investment, construction employment and long-term expansion.
If completed as proposed, Project Obsidian would establish one of the nation’s first commercial superhot rock geothermal power facilities, with Newberry Volcano providing the underground heat resource for a new source of continuous electricity generation in Oregon.