Oregon and Washington are advancing one of the Pacific Northwest’s most expensive transportation infrastructure projects, a proposed $14.4 billion replacement of the Interstate 5 bridge spanning the Columbia River between Portland and Vancouver, as escalating construction estimates, multibillion-dollar funding obligations and questions surrounding prospective contractors intensify the financial challenges facing the undertaking.
The Interstate Bridge Replacement Program, jointly administered by the Oregon Department of Transportation and Washington State Department of Transportation, has reached a significant procurement milestone after Columbia River Constructors emerged as the only consortium to submit qualifications for the primary bridge construction contract. The development places a multibillion-dollar public investment on a contracting path with limited competition as transportation officials prepare to negotiate costs and secure financing for a project expected to reshape interstate commerce for decades.
The proposed replacement extends beyond two bridges across the Columbia River. Approximately five miles of Interstate 5 are included in the undertaking, encompassing highway improvements, interchange reconstruction, transit infrastructure, pedestrian and bicycle facilities, and modifications to the surrounding transportation network. Its financial implications reach throughout Oregon, where Interstate 5 connects agricultural producers, manufacturers, distribution centers, ports and communities from the California border to Washington.
The latest program estimates place the overall undertaking between $13.5 billion and $15.2 billion, with $14.4 billion identified as the most likely cost. That figure represents a substantial increase over the $5 billion to $7.5 billion planning estimate developed in 2022.
Approximately $7.8 billion of the current estimate accounts for anticipated base project costs, while another $6.6 billion covers inflation, financial uncertainty and construction risks. The difference between the midpoint of the original 2022 estimate and the current projection exceeds $8 billion, substantially altering the financial obligations confronting transportation agencies in both states.
Despite significant public financing commitments, approximately $5.7 billion has been identified through federal grants, state appropriations, transportation funding and projected toll financing, leaving a considerable funding gap.
Federal participation includes $1.5 billion through the Bridge Investment Program and another $600 million through the federal Mega grant program. Oregon has committed $1 billion through state legislation, while Washington has identified $350 million in state funding and approximately $650 million in federal formula transportation funds.
The financial plan also anticipates approximately $1.5 billion supported by tolling. Additional federal transit assistance remains under consideration, including a proposed $1 billion investment through the Federal Transit Administration’s Capital Investment Grant program.
Federal acceptance of the program’s initial financial plan represents a procedural milestone, although billions in additional financing remain necessary to complete the corridor. Transportation officials are pursuing a phased construction strategy that would allow portions of the project to proceed as funding becomes available.
Meanwhile, the procurement process for the principal construction contract has introduced additional financial questions.
Columbia River Constructors, a consortium involving Guy F. Atkinson Construction, Traylor Bros. Inc. and Kiewit Engineering Group, emerged as the sole respondent to the qualifications process for the proposed Columbia River crossing. The contract is estimated at approximately $3.3 billion to $3.9 billion, making it one of the largest individual expenditures within the broader transportation program.
Oregon and Washington are pursuing a progressive design-build arrangement that would involve the selected contractor in engineering and cost development before a final construction agreement is negotiated. The absence of competing qualifications submissions has attracted attention from elected officials responsible for monitoring the project’s financial management.
During a November 16 meeting of the Joint Oregon-Washington Legislative Action Committee, Oregon legislators Thủy Trần and Bruce Starr raised questions concerning cost controls and contractor accountability, while Washington legislator Ed Orcutt addressed the financial implications of limited competition. Other committee members acknowledged that relatively few construction firms possess the engineering capacity and financial resources necessary to undertake a bridge project of this magnitude.
The consortium remains subject to additional evaluation and contractual negotiations, with contractor selection anticipated in 2027.
Questions surrounding the procurement have also directed attention toward the construction history of companies participating in Columbia River Constructors, particularly Kiewit Engineering Group and related Kiewit construction operations.
Kiewit has participated in several major bridge projects that experienced substantial budget increases, construction delays or contractual disagreements, including projects in Oregon and Maryland.
Among those projects is the Interstate 205 Abernathy Bridge improvement near Oregon City, where early planning estimates of approximately $250 million in 2018 have been followed by project costs approaching $800 million. Construction has also experienced delays extending more than two years beyond earlier scheduling expectations.
The financial increases span years of planning, engineering and construction, during which inflation, project scope and other expenses have changed. The difference between early estimates and subsequent costs does not independently establish the amount attributable to contractor performance.
Kiewit was also selected in 2024 for design work associated with the proposed Hood River–White Salmon Bridge replacement, another interstate crossing connecting Oregon and Washington. Estimates for that undertaking have subsequently exceeded $1.2 billion, with engineering requirements, foundation construction expenses and inflation contributing to the higher projections.
Separate reporting on Kiewit’s Oregon construction record has identified unfavorable contractor performance evaluations in four consecutive annual reviews beginning in 2022, adding another consideration to the examination of the company’s qualifications.
Outside Oregon, Kiewit’s involvement in the replacement of Baltimore’s Francis Scott Key Bridge ended in April 2026 when Maryland officials declined to continue with the company for the next phase of the project following disagreements concerning proposed construction costs and scheduling expectations.
The Maryland decision reflected a state procurement determination rather than a finding of contractor misconduct. Kiewit has defended its broader construction record and experience delivering major transportation projects, and no finding of wrongdoing has been established in the Interstate 5 procurement.
Beyond the contracting process, the replacement involves extensive reconstruction of one of the region’s busiest commercial transportation corridors.
The existing Interstate 5 crossing consists of two aging lift bridges. The older northbound structure opened in 1917, while the southbound bridge entered service in 1958. Both remain in operation as transportation officials pursue replacement infrastructure intended to accommodate modern highway traffic and regional growth.
The project calls for two fixed-span bridges incorporating wider shoulders, transit facilities and accommodations for pedestrians and bicyclists. The proposed configuration includes three through lanes and an auxiliary lane in each direction, alongside interchange improvements intended to address congestion.
In January 2026, the United States Coast Guard approved a proposed fixed-span configuration providing approximately 116 feet of navigation clearance above the Columbia River, eliminating the bridge lifts that currently interrupt interstate traffic when certain vessels pass through the crossing.
The design also carries financial consequences for river-dependent industrial operations. Agreements announced in 2025 provide approximately $140 million in combined compensation to four businesses potentially affected by navigation clearance limitations associated with the replacement.
The project’s economic reach extends beyond the Portland metropolitan area.
Interstate 5 carries commercial freight between Oregon’s agricultural regions, manufacturing centers, distribution facilities and major West Coast markets. Transportation through the Columbia River crossing connects Oregon businesses with Washington suppliers, customers and freight networks serving destinations throughout the United States and Canada.
For Southern Oregon, the corridor provides a direct commercial transportation connection between communities in Josephine, Jackson, Douglas and neighboring counties and the major markets of the Pacific Northwest.
Agricultural products, timber-related commodities, manufactured goods, consumer merchandise and commercial supplies move through the Interstate 5 network, making the reliability of the northern Oregon crossing economically relevant to businesses operating hundreds of miles from the construction site.
The projected toll financing introduces additional economic considerations for motorists and commercial transportation operators. Eventual financial obligations will depend on the rates, collection policies and financing arrangements adopted by the responsible authorities.
Current planning anticipates selection of the design-build contractor in 2027, followed by additional engineering development and the beginning of major bridge construction in 2028. The replacement crossing is targeted to begin carrying vehicles in 2035, while completion of the larger five-mile transportation program is projected as far into the future as 2045.
The extended construction timeline leaves the program exposed to future changes in labor and material costs, financing conditions, regulatory requirements and available public revenue. Although the current financial estimate includes allowances for those uncertainties, actual expenditures will depend on the final project scope, negotiated contracts and construction conditions.
For Oregon taxpayers, the undertaking represents a long-term financial commitment involving state appropriations, federal transportation investments, potential toll-supported borrowing and additional funding decisions that have not yet been finalized.
As Oregon and Washington approach a prospective 2027 contractor agreement, negotiations for the Columbia River crossing will determine a major component of the program’s financial outlook. The contract’s estimated $3.3 billion to $3.9 billion value, the participation of a single qualifying consortium and the financial histories associated with other major bridge projects have placed engineering assessments, independent cost evaluations and contractual protections at the forefront of the states’ preparations.
With construction projected to continue well beyond the opening of the replacement crossing, the $14.4 billion undertaking remains a substantial long-term commitment for both states, carrying financial implications for interstate commerce, public transportation expenditures and Oregon’s infrastructure obligations for decades to come.