After nearly a year of construction, orange barrels, nighttime closures and changing traffic patterns along Interstate 5 north of Grants Pass, the finish line is coming into view for a $25 million highway rehabilitation stretching approximately 10 miles through northern Josephine County.
The Oregon Department of Transportation project runs from approximately milepost 58.18 at North Grants Pass to milepost 66.70 near Hugo, carrying construction through the interchanges serving North Grants Pass, Merlin and Hugo. Work began in October 2025 and remains on schedule for completion this fall.
For motorists traveling regularly between Grants Pass, Merlin, Hugo and points farther north, the approaching completion will bring an end to months of nighttime lane restrictions, intermittent ramp closures and construction activity along one of Southern Oregon’s busiest transportation arteries.
The undertaking has reached well beyond a conventional resurfacing job. Crews have repaired and replaced deteriorated asphalt across travel lanes, shoulders and interchange ramps, replaced bridge joints, installed guardrail and improved roadside areas intended to provide greater recovery space for vehicles leaving the highway.
Beneath that construction is a stretch of interstate that had gone without major paving since 2009. Years of passenger traffic and heavy commercial freight produced cracking, rutting and pavement deterioration along the corridor. The rehabilitation was designed to address that damage before deterioration penetrated farther into the highway structure and required substantially more extensive reconstruction.
Much of the work is now behind Southern Oregon motorists, with crews concentrating on the remaining interchange, guardrail, paving and roadside operations as the project enters its closing phase.
Intermittent nighttime ramp closures continue at Exit 58 in North Grants Pass, Exit 61 at Merlin and Louse Creek, and Exit 66 at Hugo and Jumpoff Joe Creek. Those closures generally occur between 7 p.m. and 7 a.m., with current scheduling carrying portions of the ramp work into early October. ODOT has planned the construction so that generally only one ramp is closed at a time, although weather and field conditions can alter individual work schedules.
Guardrail replacement and related shoulder and lane operations also continue between Merlin and Hugo. Motorists can still encounter reduced lanes, temporary traffic controls and construction crews alongside the interstate even when individual interchange ramps remain open.
Commercial carriers face additional restrictions during the final portion of the project. Southbound I-5 between the Hugo area and North Grants Pass has been subject to a nighttime 12-foot width restriction for oversized loads, with the current restriction extending into mid-October. Alternate interchanges have been identified for commercial vehicles requiring turnaround options while ramps are unavailable.
At Hugo, part of the work carries importance well beyond the current construction season. Improvements at the interchange include additional maneuvering room for large trucks when winter weather shuts down I-5 across the mountain passes to the north.
Hugo lies south of Sexton, Smith and Stage passes, where snow, ice, crashes and severe winter conditions can halt interstate traffic. The expanded maneuvering area provides another location for commercial vehicles to reverse direction before reaching a closure, strengthening traffic-management capability along the principal highway connecting Southern Oregon with the rest of the state.
The project is currently valued at approximately $25 million. Earlier planning documents placed the overall estimate near $20.2 million, including approximately $18.9 million for construction. Current ODOT project information reflects the higher figure, although available agency documents do not identify a single cause accounting for the difference between the earlier estimate and the present project cost.
The rehabilitation represents a substantial highway investment along a section of I-5 carrying local commuters, interstate travelers, emergency vehicles and commercial freight through Josephine County every day.
After nearly four seasons of construction, the familiar work zone north of Grants Pass is beginning to recede. Pavement rehabilitation, bridge work, guardrail replacement and interchange improvements have moved into their later stages, leaving a narrowing list of operations between crews and completion.
Nighttime restrictions will continue while that work is finished, particularly around the North Grants Pass, Merlin and Hugo interchanges. But with ODOT maintaining its fall 2026 completion schedule, a project that has shaped travel through northern Josephine County since last October is approaching its final miles.